This Project Development and Environment
(PD&E) study involves evaluating the widening of Lennard Road from
Walton Road to Savanna Club Boulevard (Segment 1); extension of Lennard Road from
Savanna Club Boulevard to Tilton Road (Segment 2); and extension from Kitterman Road to U.S. 1
(Segment 3). St. Lucie County is currently designing the link between
Segments 2 and 3 within a Municipal Service Benefit Unit (MSBU). The
project study area and the project limits for Lennard Road are
illustrated on Figure 1.
The City of Port St. Lucie has widened Lennard Road from its southern
terminus at U.S. 1 to Walton Road. Within the project limits, Lennard Road exists as a two lane
roadway from Walton Road to Port St. Lucie High School. The proposed extension of Lennard Road is located in
unincorporated St. Lucie County. The total length of this project
excluding the MSBU segment is approximately 3.6 miles.
This PD&E study will evaluate the following:
• widening existing Lennard Road from two to four lanes from Walton Road
to it’s northern terminus in the vicinity of Port St. Lucie High School;
• extending Lennard Road from it’s existing northern terminus north to
the MSBU project; and,
• extending Lennard Road from the MBSU project at Kitterman Road to U.S. 1.
Other improvements will include sidewalks and bicycle accommodations,
modifications to the existing stormwater management system to provide
water quality and quantity treatment, and intersection improvements.